Data-centre graft: MACC identifies two more companies

TheEdge Sun, Jul 20, 2025 05:58pm - 2 days View Original


KUALA LUMPUR (July 20): The Malaysian Anti-Corruption Commission (MACC) has identified two more companies suspected of obtaining data-centre construction projects by bribing the project manager of a prominent construction company, who was recently arrested.

According to a source, several company directors have also been identified and will be called to assist in the investigation into the case.

"The investigation also found that the main suspect, the project manager, admitted to having asked for about 3% of the project value from any company that wanted to obtain a project from a prominent construction company," he said here on Sunday.

The source informed that the bribe was done by leaking the tender price, and helping to ensure that the company that paid the bribe was given priority to win the tender.

"This bribe was paid in stages, according to the progress of the project payment, and it is understood that there are several million more that have yet to be paid by the company to the suspect, as per their agreement," he said.

The media previously reported that a project manager of a prominent construction company who was detained for investigation into a corruption case involving the procurement of a data-centre construction project tender, was willing to burn almost RM1 million in cash to destroy evidence, after being shocked by the MACC raid through Op Ways on Thursday.

According to sources, during the raid conducted at his home in Petaling Jaya, a team of officers found RM100 banknotes, totalling almost RM1 million, in flames.

As a result of a thorough inspection of the home, the MACC also found cash totalling approximately RM7.5 million stored in several pillow boxes; three Rolex, Omega and Cartier watches; as well as jewellery such as rings and gold coins.

On Friday, the media reported that a contract manager, his wife and two men in their 40s to 60s were arrested by the MACC investigation division around the Klang Valley, believed to be involved in corruption involving the procurement of a data-centre construction project tender in Johor, worth approximately RM180 million.

Uploaded by Liza Shireen Koshy

The content is a snapshot from Publisher. Refer to the original content for accurate info. Contact us for any changes.






Comments

KC Chiok
Like · Reply
Here are the key developers and operators involved in the growth of Johor’s data‑center ecosystem in Malaysia:



? Major Developers & Operators in Johor

YTL Data Center Holdings (YTL DC / YTL Power)
• Leading developer of the YTL Green Data Center Park in Kulai, Johor, a flagship 500 MW hyperscale campus supported by on-site solar power, with Phase 1 (~72 MW) launched in Q4 2023–early 2024, co-developed with Sea Ltd. 

Telekom Malaysia & Singtel (Nxera)
• The TM–Nxera joint venture broke ground in July 2024 on a 64 MW AI‑ready data‑center campus in Iskandar Puteri, scalable up to 200 MW, LEED-certified and using liquid cooling for high‑density workloads. Target commercial operations by 2026 .

Yondr Group
• Amsterdam‑based Yondr acquired ~73 acres in Sedenak Tech Park (Iskandar/Kulai) to build a 200 MW hyperscale campus, with Phase 1 scheduled for delivery in 2024 .

BrightRay (DC‑Science)
• Malaysian modular data‑center specialist BrightRay commissioned MY‑01, a 90‑MW campus in Sedenak Tech Park in May 2025. It’s the first of three planned facilities, delivered within eight months using prefab modular design .

STT GDC (and affiliate GDS)
• STT GDC is building a 120 MW campus in Nusa Cemerlang Industrial Park (Johor) with expectations to complete the first 16 MW building by 2025.
• Its affiliate GDS is also active in Johor through developments at Nusajaya Tech Park and part of YTL’s Green Park .

ESR‑Logos / UEM Sunrise
• A partnership between Logos Infrastructure (ESR) and UEM Sunrise is developing a potential 350+ MW data‑centre campus in Gerbang Nusajaya, Johor. The collaboration leverages UEM’s landbank and is backed by state agencies .

Stack (US hyperscaler)
• Stack is developing a 220 MW Johor Bahru campus (first phase ~120 MW, second ~100 MW), expected online by Q4 2026. It’s the largest project in Stack’s Asia‑Pacific portfolio .

ZData (Chinese firm)
• ZData Technologies has acquired ~38 acres in Gelang Patah for a new data‑center project expected by late 2025. Additional land deals also underway .



? Summary Table

Developer / JV Location Planned Capacity Status / Timeline
YTL DC / Sea Ltd. Kulai (Green Park) 500 MW total Phase 1 (72 MW) live Q4 2023–2024
TM–Nxera (TM + Singtel) Iskandar Puteri 64 → up to 200 MW Ground broken mid‑2024; full scale by 2026
Yondr Group Sedenak Tech Park 200 MW Phase 1 in 2024
BrightRay (DC‑Science) Sedenak Tech Park 90 MW MY‑01 live May 2025
STT GDC / GDS Nusa Cemerlang / Nusajaya 120 MW+ First building by 2025
ESR‑Logos / UEM Sunrise Gerbang Nusajaya ~350 MW Planning stage (2024–25)
Stack (USA) Johor Bahru 220 MW Phase 1 by late 2026
ZData Technologies Gelang Patah Undisclosed (land acquired) Project expected by late 2025




? Why Johor is attracting data‑center development
• Proximity to Singapore’s submarine‑cable hub, offering low‑latency connectivity for global clients.
• Abundant land, water, and power supply (often coal‑based, but renewable in YTL’s case).
• Streamlined regulatory environment and government support, especially under Johor–Singapore Special Economic Zone goals.
• Massive investments from hyperscalers including Microsoft, Oracle, ByteDance, and others intensify demand for third‑party infrastructure in Johor         .



Let me know if you’d like deeper detail about any specific developer or project timeline—happy to dig into capacity phases, operator strategies, or construction updates.
Show more
wai shun liew
Like · Reply
try to search 180million data center project in johor then u know which company kena
Tteffub Nerraw
No need search lah... monday who LD, who is the one.
Like · 2 days · translate
eric leow
Like · Reply
oh dear, anyone holding dc related share take care

Login to comment.